dws-tvo-teignmouth-seawall-repair-770pxThe Environmental Agency confirmed that repairs to the Teignmouth's seawall were finished within three months after storm Frank hit the coastal town on the south west coast of England.

The agency worked with Teignbridge District Council and contractors Team Van Oord to secure the seawall for the future.

Conditions during the repair work were challenging, with continued storms, bad weather, and access for machinery only possible on the low tides around spring tides.

dws-tvo-teignmouth-seawall-hole-sand-350
 Following the repair of the sea wall, a geotextile liner was put in place and the hole could be filled with soil again.

Instability of the wall
Teignmouth was hit by storm Frank on 28 December last year. A break in the sea wall allowed tonnes of material to be sucked out from under the promenade and after a few days a 2m deep sink hole appeared.

As waves continued to lash the seafront, immediately after the storm, work began on an emergency repair.

It was essential to carry out these repairs quickly as the instability of the wall and promenade threatened increased flood risk to homes and possible safety risks for the public.

Night work
Environment Agency staff were only able to work on the beach for a few hours at a time, for a few days at a time, and often had to work during the night.

Thom Buxton-Smith, for the Environment Agency, said: "Despite these challenges we worked with Team Van Oord to complete the repairs quickly. The voids have been filled beneath the promenade, slipway and car park. We have repaired the limestone masonry sea wall and installed steel sheet piling at the base of the wall to stabilise it"

This news item was originally published on the official website of the UK government.


Read also on this website
Flood & Coast 2016: Environment Agency excellence awards for flood projects by BAM, Team Van Oord and VBA, 26 February 2016
Flood & Coast 2016: Dutch and British flood experts seek cooperation on asset resiliency and community involvement, 24 February 2016
Portsmouth City Council praises quick response Team Van Oord after sea wall collapse, 22 January 2016


More information
Team Van Oord
Small Dole, UK
+44 1273 494 843
www.teamvanoord.com

Twitter

Dutch Water Sector

@HollandWater

21 hours ago

The #Beira Municipal Recovery and Resilience Plan to rebuild the city has been released. The plan has been compiled… https://t.co/emDiPgovfy

Dutch Water Sector

@HollandWater

23 hours ago

Explained: #Netherlands’ ‘Room for the River’ project that #Kerala CM wants to replicate @IndianExpresshttps://t.co/F8gBLZiuKW

Worldwide Projects

Upcoming Events